Hello!
I'm an engineer by training, so I'll leave the long narrative writing to Peter. Here we'll be documenting our progress on the build. Since it's winter in MN, we're in planning mode. We see our upcoming schedule as the following: Dec. 2019 - Jan. 2020 - Design Development, Contractor Selection, Jan. - Mar. - Construction Documents, City Review Process Apr. - Demolish Garage, Move Electrical Wiring; Move Magnolia Tree; Dig Foundation May-Jun. - Foundation. Post and Beam, and Roof Construction July - Strawbale Wall construction! Aug. - Plastering, Electrical, Mechanical, Plumbing Sept. - Nov. - Interior Work -Katie